Customer App
HealthyPRJ-2026-0003
Foresight Retail
Planning
22%
Project Manager
Aiman Foo
Start
14 Aug
Target
15 Nov
Project Value
RM 248,000
Project finance data will be permission-restricted when RBAC is connected.
Current Project Value
RM 248,000
Original value plus approved changes
Collected
RM 20,300
Billing received
Outstanding
RM 227,700
Remaining balance
Current Margin
94.4%
Based on current mock actual cost
Project finance summary
- Original Project Value
- RM 248,000
- Approved Changes
- RM 0
- Estimated Cost
- RM 11,800
- Actual Cost
- RM 13,800
- Estimated Profit
- RM 236,200
- Actual Profit
- RM 234,200