Corporate Website

Watch

PRJ-2026-0002

Meridian Holdings

UAT
84%
84% Complete

Project Manager

Ethan Lim

Start

03 Jun

Target

12 Sept

Project Value

RM 72,000

Upcoming milestones

Major delivery checkpoints, not just task progress.

Discovery Complete

MIL-00001 · Owner: Nadia Rahman

14 Aug
Completed

UI/UX Approved

MIL-00002 · Owner: Maya Tan

24 Aug
Completed

Core Development

MIL-00003 · Owner: Hakim Zain

05 Sept
In Progress

Internal QA

MIL-00004 · Owner: Sofia Lee

10 Sept
Upcoming

Client UAT

MIL-00005 · Owner: Yusuf Rahman

15 Sept
Upcoming

Production Deployment

MIL-00006 · Owner: Hakim Zain

25 Sept
Upcoming

Handover

MIL-00007 · Owner: Nadia Rahman

30 Sept
Upcoming

Completion control

Project cannot be closed until the closure checklist is satisfied.

Development
QA
QA Passed
UAT
Client UAT Approval
Deployment
Production Verification
Handover
Documentation
Training
Final Commercial Clearance
Warranty
Warranty Completed
Project Closed
Scope delivered
UAT signed
Production deployed
Documentation delivered
Credentials handed over
Training completed
Final invoice issued
Required payment received
Warranty dates established
Project retrospective completed