HR Workflow Automation

Healthy

PRJ-2025-0015

Helio Care

Completed
100%
100% Complete

Project Manager

Ethan Lim

Start

07 Nov

Target

18 Feb

Project Value

RM 96,000

Project scope

HR Workflow Automation scope hierarchy: Project to Module to Feature. Tasks and issues link to features later.

Authentication

3 Features · 9 Tasks

Owner

Hakim Zain

Status

Completed

Due

22 Aug

100%
Login
Completed
Password Reset
Completed
Role Access
Completed

Patient Management

3 Features · 10 Tasks

Owner

Sofia Lee

Status

Testing

Due

03 Sept

90%
Patient Profile
Testing
Patient History
Completed
Search
Testing

Appointment Management

4 Features · 12 Tasks

Owner

Yusuf Rahman

Status

In Development

Due

08 Sept

78%
Create Appointment
Completed
Cancellation
Completed
Reschedule Appointment
In Development
Availability
Planned

Reporting

2 Features · 5 Tasks

Owner

Nadia Rahman

Status

Planned

Due

20 Sept

20%
Appointment Report
Planned
Patient Report
Planned